Erection Sequence



1. Bolt column to anchor bolts

2. Bolt rafters to column

3. Bolt purlins to rafters



4. Bolt canopy eave strut

5. Ceiling joist to ceiling rafter

6. Optional vaulted ceiling joist



7. Complete bay

8. Southridge red iron

9. Autumn View red iron



10. Screw roof panels

11. Make sure panels are level
and screw lines are straight

12. Foam closures



13. Lay vented ridge

14. Lay ridge cap

15. Make sure it's square



16. Screw ridge roll

17. Drill wedge anchor hole

18. Install anchors in stud track



19. Studs plumb and level

20. Screw studs

21. Screw stud strapping



22. Install windows and doors

23. Walls can be anywhere

24. Ready for siding



25. Roll out reflective insulation wrap

26. Screw starter strip
(Wrap not shown for clarity)

27. Screw siding
(Wrap not shown for clarity)



28. Lock on next panel
(Wrap not shown for clarity)

29. Screw vented soffit

30. Finished home




Contact Us

Email Us:info@freedomsteelhomes.com
 
Phone Us:1.800.630.2846
 
Write Us:160 Congress Park Drive
Delray Beach, FL 33445

Request A Quote

  Please use this form to request more information on any of the homes you see:

Copyright © 2010 Freedom Steel Building Corporation All Rights Reserved. Privacy Policy